Steering committee meetings that end in a decision

The steering committee meets once a month. The deck runs to forty slides. The project manager walks through status for most of the hour, the sponsors ask a few questions, and the meeting ends with “let’s take that offline.”

Next month the same vendor problem is back, on slide 12 this time, and a month worse.

A steering meeting that doesn’t make decisions is an expensive status update. The fix is not a better deck. It is a different agenda.

Why steering meetings turn into status updates

Most steering committees were set up to make decisions a project team can’t make alone: money, scope, dates and trade-offs between projects. Over time they drift. Here is why:

If a steering meeting could have been an email, the decisions were never on the agenda.

Build the agenda around decisions

You don’t need a new governance framework. Change how the next meeting is run.

  1. Send status before the meeting, not during it. Share the brief two days ahead and assume people have read it. Spend the first five minutes on questions about it, not on presenting it.
  2. Put decisions first. The first item on the agenda is “Decisions needed today.” Everything else comes after.
  3. Bring only what the committee can decide. If the project manager or sponsor can decide it alone, they should. The committee’s time is for money, scope, dates and conflicts between projects.
  4. Close by reading back. In the last five minutes, read out each decision made and each action agreed, with an owner and a date. If nobody will own it, it wasn’t agreed.

Write a decision request people can answer in five minutes

Most of the work happens before the meeting. A good decision request fits on half a page and has five parts: what is being decided, two or three options, the cost of each, your recommendation, and the date after which waiting costs more.

Example: data migration is three weeks late.
Option A: accept the delay. Go-live moves from January 12 to February 2. No extra cost.
Option B: add a contractor for $40,000 and keep January 12. Risk: a new person on the data in the final weeks.
Option C: migrate two years of history instead of seven and keep January 12. Older records stay in the archive system, read-only.
Recommendation: C. Finance confirmed it needs only two years for reporting.
Decide by: November 26. After that, C no longer saves the date.

Compare that with “the migration is behind and we’re looking at options.” The first version gets a decision in five minutes. The second gets a follow-up meeting.

Record it, or it didn’t happen

Every decision goes into a decision log on the day it is made. For each one, record what was decided, who decided, when, why, and which options were turned down. Each action gets an owner and a due date, and the next meeting starts by checking them.

This takes a few minutes. It pays off in month six, when someone asks why the project dropped five years of history. The answer is in the log, with the reason and the names, instead of in three people’s memories.

How to tell it’s working

The short version

A steering committee exists to make decisions. Send status ahead, put the decisions first, bring each one with options and a recommendation, and write down what was agreed before everyone leaves the room.