Measure capacity from assigned work, not planned percentages

Ask most PMOs how busy someone is and you get a number from a resource plan: “Priya is 50% on the CRM migration.” That number was agreed at kickoff, typed into a spreadsheet or a resource request, and rarely touched again.

The work did not stay still. Tasks were added, dates slipped, and Priya picked up two things nobody wrote down. The 50% still looks fine. It just isn’t true anymore.

A planned percentage describes intent, not work

Planned percentages are useful at the start. Before a project has a schedule, “we need half of a data engineer for six months” is the best you can do. The problem is that most PMOs keep using that number long after the real work exists.

Here is what goes wrong:

A planned percentage is a hope. An assigned task is a commitment.

Assigned work is what people are actually doing

Your project managers already keep a list of who is doing what, and when: the schedule. Each task has an owner, dates, and some share of that person’s time. Add those up across every project and you have a capacity number that is grounded in real work.

Back to Priya. Her plan says 50% on the CRM migration. Her tasks this month say something else: data mapping has slipped into the testing window, so she has three tasks running at once that add up to about 80% of her time. The plan says she has room for the new reporting project. Her tasks say she does not.

Measuring from assigned work gives you four things a planned percentage cannot:

How to make the switch

You do not need a big change programme. Start with the next planning cycle.

  1. Make real work a task. Every piece of work that takes meaningful time gets a task with an owner and dates. Week-sized chunks are fine. You do not need hourly detail.
  2. Put the time on the task, not the person. “Priya, 60%, data mapping, weeks 44 to 47” is more useful than “Priya, 50%, CRM project.”
  3. Use planned percentages only before tasks exist. They are fine for early staffing. Once someone has tasks on a project, the tasks win.
  4. Take time off out of capacity. Holidays, leave and standing duties like a support rotation reduce what someone can take on. Count them, or your numbers will look better than they are.
  5. Review one view every week. Look at capacity against demand from tasks across the whole portfolio. Act on anyone above 100% for more than a week or two.

“But our project managers won’t keep tasks up to date”

This is the most common objection, and it is worth taking seriously. But consider the alternative. If tasks are out of date, planned percentages are further out of date, because nobody looks at them at all. Schedules at least get opened every week. Building capacity on the thing people already maintain is the more reliable choice.

Two other objections come up:

The short version

Planned percentages tell you what you hoped would happen. Assigned work tells you what is happening. If your PMO is going to say yes or no to new work based on capacity, base it on the work people are actually assigned.