The riskiest moment in any project isn’t the build — it’s the night you cut over. And the most dangerous go/no-go meetings are the confident ones, where everyone nods, nobody has the exit criteria in front of them, and “we’ve come too far to stop now” quietly becomes the decision-making framework.
A go/no-go call should be boring. Boring means you decided the criteria in advance and you’re simply checking them. Here are the twelve questions that get you there.
Readiness
- Are the exit criteria written down, and are they actually met — zero critical/high bugs, UAT signed off, performance within SLA?
- Has the full cutover run-sheet been rehearsed end to end, not just discussed?
- Is the data migration validated against production-scale volumes, with a trial run behind you?
- Are smoke tests defined for the moment after cutover, before you open the doors?
People
- Have end users, admins and support been trained, with quick-reference guides in hand?
- Are accounts and permissions provisioned and tested — not something you’ll “sort out live”?
- Has the comms plan gone out, so nobody’s surprised the system changed under them?
- Is the war room staffed — cross-functional leads in one channel, ready to triage?
Safety
- What are the exact rollback triggers? “We’ll know it when we see it” is not a trigger.
- Has the rollback procedure itself been tested — can you actually get back to the last known good state?
- Who holds decision authority — by name — to call go, no-go, or abort mid-cutover?
- What’s the hypercare plan — who’s on high alert, for how long, after you’re live?
The thing every rollback plan forgets
Teams lovingly document how to roll back — and forget to decide who can pull the trigger and when. At 2 a.m., with a half-migrated database and a VP asking for “five more minutes,” you do not want to be debating authority. Assign it in daylight: one accountable person, clear triggers, no ambiguity. A rollback you’re too hesitant to call isn’t a safety net — it’s decoration.
Flip the switch when the criteria say so — not when the room runs out of patience.