Open ten status reports and you’ll find at least three projects reporting a Cost Performance Index of exactly 1.00. On plan! Perfectly healthy! Except half of them are quietly on fire. A clean 1.00 is rarely a measurement — it’s a default, and defaults are where bad news goes to hide.
Earned value isn’t hard, but it is precise. Get the three inputs right and CPI/SPI become the most honest numbers on your dashboard. Get them wrong — or let a tool fake them — and you’ve built your steering committee a very confident lie.
The three numbers that matter
- BAC — Budget at Completion. What the whole project is authorized to cost.
- EV — Earned Value. How much of that budget the work actually done represents. Not hours burned — value delivered.
- AC — Actual Cost. What you’ve truly spent to get there.
From those: CPI = EV ÷ AC (above 1.0 = under budget) and SPI = EV ÷ PV, where Planned Value is how much you should have earned by now. Simple arithmetic — the danger is entirely in the inputs.
Where the fake 1.00 comes from
Most tools store CPI and SPI as fields that default to 1.0 and are never actually computed. A brand-new, empty project shows a flawless 1.00 — and because it’s green, nobody questions it. The number survives all the way to the executive briefing, right up until the overrun is undeniable.
The fix is a rule, not a formula: when the inputs for a metric are missing, show “—”, never 1.00. A dash prompts a question (“why don’t we have actuals yet?”). A fake 1.00 ends the conversation.
Earn value by task, not by vibe
A single project-level “percent complete” slider is easy to game — finish the cheap, easy tasks first and your number races ahead of reality. Cost-weighting fixes it: each task contributes its own cost, weighted by how complete it is. Clear the expensive, critical work and your earned value climbs honestly; clear the trivial stuff and it barely moves. A project that’s “80% done” but has only finished its cheapest tasks will — correctly — show a lower earned value.
Measure schedule against the plan you actually agreed to
SPI is only as honest as what it’s measured against. A flat calendar line spread evenly across start and end is better than nothing, but it assumes work arrives at a constant rate, which it never does. Measure against your baseline’s time-phased schedule and SPI finally reflects the plan your sponsor signed off on — the kind of number you can defend when someone pushes back.
The 60-second read
Next status meeting, run this on any green project: ask what its EV, AC and BAC are. If no one can answer, the 1.00 is decorative. Real earned value takes a budget, a baseline, and a little discipline about where “actual” comes from — and in return it tells you the truth early enough to do something about it.